Project Location:

Parwan, Afghanistan

Client:

U.S. Army Corps of Engineers (USACE) – Philadelphia District

Client Needs and Requirements:

There were five facilities constructed by another contractor. The electrical work was subpar and required removal and replacement with a code-compliant installation.

Challenges and ISI’s Response:

Logistics and coordination were major factors due to the expedited schedules required by the client. Coordination for access to the buildings was difficult since they were occupied during the renovations. ISI rearranged sequences of events multiple times to accommodate the customer’s needs, and still finished the projects on schedule and within budget.

The Results:

The facilities at Parwan now have a code-compliant safe electrical system which will provide years of reliable service.

The Details: