Project Location:
Area 82 – Bagram Airfield (BAF), Afghanistan
Client:
U.S. Army Corps of Engineers (USACE) – Philadelphia District
Client Needs and Requirements:
The U.S. Military required construction for a new 12,000 square foot warehouse with interior offices, including electrical and HVAC construction.
Challenges and ISI’s Response:
The shipping route through Pakistan was blocked, which caused the original Period of Performance to be extended. ISI found an unconventional northern route to move equipment and personnel to the site, and worked extended hours to meet the new schedule.
The Results:
ISI completed the job and within budget, and to the client’s satisfaction.
The Details:
In addition to the new construction of the 12,000 square foot warehouse, ISI completed the following activities:
Completed site preparation tasks
Constructed structural foundations, slab-on-grade, warehouse,
Installed electrical and HVAC for the interior of the building
Built sidewalks, concrete stoops, and a sloped concrete entry into the warehouse.