ISI Successfully Completes Major Turbine Overhaul at BAF

ISI recently completed a sucessful major turbine overhaul of Combutsion Turbine 03 and 04, replacing the Turbine Engines and rebuilding the Reduction Gear Boxes per manufacturer recommendations.  This task had a 116-day period of performance and it was successfully completed ahead of schedule (in 91-days) and on budget.  During the performance of this work there were no interruptions to Bagram Airfield.

 